Amgen, Dún Laoghaire – Ireland

 

 

Dornan was commissioned to fit out a new three-storey manufacturing facility to increase capacity, connected to the existing warehouse at Level 1. This also involved installing new process utility generation equipment, and a new electrical substation in the existing production module.

Extraordinary solutions

  • Modular cleanroom panelling with walk-on ceiling
  • Integrated syringe filling line
  • Motorised fire & smoke dampers

13 AHUs with auxiliary equipment

16 process stainless steel exhaust systems

Phoenix air control valves